HDPE Protection of Jetty Piles (Including Above and Underwater Repairs of Jetty Piles)

İşveren             : BOTAŞ-Petroleum Pipelines Co.-LNG Terminal-Marmara Ereğlisi/Tekirdağ

Başlangıç Tarihi : 30.07.2019

Bitiş Tarihi          : 06.12.2021

Kapsam             : 

 

  1. Repair existing jetty piles with cement based, high-strength repair material above the splash-zone, thickness 0.00 – 150.00 mm, 1,202.99 sq.m

  2. Repair existing jetty piles with epoxy putty within splash-zone and  under water, 238.78 sq.m

  3. Epoxy painting of steel jetty piles above the splash-zone, 1,188.20 sq.m

  4. Repair existing steel jetty piles with epoxy putty within splash-zone and  under water, 86.05 sq.m

  5. Supply and apply protective HDPE jacketing system on steel jetty piles, 266.28 sq.m

  6. Apply concrete surface protection material on bottom and side surfaces of jetty structural concrete elements, 8,393.11 sq.m

  

2
3
4

Repair Existing Jetty Piles with Cement Based Material Above the Splash-zone

5
6
7

Repair Existing Jetty Piles with Epoxy Based Putty within Splash-zone and Under the Water

Painting Existing Steel Jetty Piles with Epoxy Based Paint above the Splash-zone