Strengthening of AI Quay (3rd Stage)
Employer : İSDEMİR-İskenderun Iron and Steel Co. – İskenderun, Hatay, Türkiye
Start Date : 16.11.2020
Finish Date : 26.05.2022
Scope of Work :
1. Replacement of Precast Concrete Beams at 500 m Section of AI (No.1) Dock (4,400.00 sq.m)
1.a. Dismantling precast concrete beams, 500.00 nos, 4,330.00 tons
1.b. Manufacturing and installation of precast concrete beams, 500.00 nos, 4,330.00 tons
1.c. Manufacturing and installation of precast concrete beams, 500.00 nos, 4,330.00 tons
1.d. C30/37 ready-mixed concrete, 1,690.71 cu.m; reinforcement, 536.14 tons
1.e. Formwork, 8,527.48 sq.m
1.f. Installing the dismantled concrete beams as breakwater reinforcement, 2,975.28 cu.m
2. Strengthening the reinforced concrete system under the dock at 300 m long section, 11,074,71 sq.m
2.a. Demolish rf concrete surface and prepare for repair mortar application, 11,074.71 sq.m
2.b. Reinforcing steel, 234.75 tons
2.c. Cement based, high-strength special repair mortar, 2,550,565.00 kgs
2.d. Drilling rf concrete and fixing rf steel anchors using epoxy, 104,020.00 nos
2.e. Application of concrete surface protection material, 10,866.30 sq.m
3. Replacement of pavement concrete on 500 m long section of AI (No.1) dock, 4,070.00 sq.m
3.a. Steel mesh, 23..60 tons
3.b. Formwork, 445.32 sq.m
3.c. C30/37 ready-mixed concrete, 814.40 cu.m



Replacement of Precast Concrete Beams at AI (No.1) Dock-Installation of Precast Beams
Replacement of Precast Concrete Beams at AI (No.1) Dock-Shear Keys


Installation of Precast Beams and Pouring Dock Concrete Pavement


Repair of Fender Beam at AI (No.1) Dock