Employer : Global Terminal Services Co.
Start Date : 20.03.2023
Finish Date : 28.12.2024
Scope of Work :
1. Repair Damages on Pile-Beam Connections and Other Sections of Existing Concrete Elements of the Jetty (8,454.28 sq.m)
1.a. Breaking rf concrete surfaces, thickness between 30.00 – 100.00 mm
1.b. Cleaning the concrete surface after breaking
1.c. Application of cement based corrosion protection material
1.d. Concrete repair using high-strength, cement based repair material, thickness between 30.00 – 100.00 mm
1.e. Application of cement based elastomeric water insulation material over the repaired surfaces
Pile Cap After the Earthquake, Before Strengthening
Breaking Damaged Concrete up to Durable Concrete is Achieved
Cleaning of Concrete and Existing Reinforcement Surfaces
Concrete Repair with High Strength Repair Mortar
Reinforced Concrete Elements after Repair Work is Fully Completed
Employer : Global Terminal Services Co. – Dörtyol, Hatay, Türkiye
Scope of Work (contnd) :
2. Jetty Repair Works
2.a. Water Repellent material Application on Un-repaired Faces of Reinforced Concrete Elements of the Jetty (35,100.00 sq.m)
2.b. Manufacturing and Installation of Special Sliding Steel Connection Elements at Expansion Joints (2×72.00 nos)
2.c. Painting of the Unprotected Parts at the Joints of Steel Pipe Piles with Concrete (1,305.00 nos steel piles)
2.d. Replacement of Damaged or Missing HDPE Jackets on Steel Pipe Piles (disassembly and assembly works) (133.00 nos steel piles)
2.e. Concrete Repair at Expansion Joints (48.00 sqm)
2.f. Reconstruction of Demolished Marine Shelter Masonry Wall
Application of Concrete Surface Protecting Material at Unrepaired Concrete Elements