Repair of Earthquake Damages and Strengthening Works at Docks 3 and 4 – İskenderun, Hatay, Türkiye

Employer          : LimakPort İskenderun International Port Management Co. 

Start Date         : 15.08.2023

Finish Date       : 07.11.2024

Scope of Work  : 

 

  1. Structural Strengthening of Steel Piles and Pile Capping Beams at Axis C & D (total piles 286.00 nos)

     1.a. Surface cleaning of existing steel piles up to elevation -2.00 m by water-jetting application

     1.b. Welding steel plates on pile surface to provide the grout is properly adhere to pile surface

     1.c. Placing 12 nos 600 mm length Ø26mm reinforcing bar anchors to capping beam around the pile including vertical reinforcement bar and spiral stirrup installation

     1.d. Manufacturing Ø1400mm diameter, 5 mm thick, bottom face closed and outer surface 500 micron epoxy painted steel jacket and installation around the pile after reinforcing              is completed

     1.e. Filling high strength flowing special grout between pile and steel jacket

     1.f. Filling the gap between grout and concrete capping beam wit high strength repair material 

Deprem Sonrası, Güçlendirme Öncesi Kazık-Beton Birleşimi
Hasarlı Başlık Betonunun Onarım İçin Hazırlanması
Mevcut Kazık Yüzeyinin Aderansının Sağlanması İçin Lama Kaynatılması

Pile Cap After the Earthquake, Before Strengthening

Welding Steel Plate for Adhering of Grout with Pile Surface

Welding Steel Plate for Adhering of Grout with Pile Surface

Betonarme Başlık Kirişinde Delik Delinmesi
Ankraj Demirlerinin Epoksiyle Montajı
Mevcut Kazık Çevresine Çelik Ceket Montajı

Drilling Holes on Pile Cap Beams

Installing Anchor Bars Using Epoxy

Steel Jacket Installation Around the Pile

Başlık Betonunun Onarılması
Çelik Gömlek İçine Yüksek Dayanımlı Özel Malzeme Doldurulması
Tamamlanmış Kazık ve Başlık Betonu

Repairing Pile Cap Concrete

Filling High Strength Special Material Inside The Steel Jacket

Pile Cap Beam and Steel Pile after Strengthening is Completed

Employer                     : LimakPort İskenderun International Port Management Co. 

Start Date                     : 15.08.2023

Finish Date                   : 07.11.2024

Scope of Work (contd.) : 

 

  2. Repair Damages on Existing Concrete Beams at Axis B & D and Another Structural Elements of the Dock (2,920.00 sq.m)

    2.a. Breaking rf concrete surfaces, thickness between 30.00 – 100.00 mm

    2.b. Cleaning the concrete surface after breaking

   2.c. Application of cement based corrosion protection material

   2.d. Concrete repair using high-strength, cement based repair material, thickness between 30.00 – 100.00 mm

   2.e. Application of cement based elastomeric water insulation material over the repaired surfaces

20
21
22
26
24
25

Reinforced Concrete  Beam Repairs at Dock

Employer                     : LimakPort İskenderun International Port Management Co. 

Start Date                     : 15.08.2023

Finish Date                   : 07.11.2024

Scope of Work (contd.) : 

 

  3. Steel Bracing on B Axis Concrete Beams (total 88 nos beams)

    3.a. Breaking rf concrete surfaces, thickness between 30.00 – 100.00 mm (728.64 sq.m)

    3.b. Drilling anchor holes (Ø35mm, L1,200.00-1,750.00mm, 2,112.00 nos)

    3.c. Provide and install anchor rod including anchoring epoxy material filling inside the hole (Ø30mm, L1,300.00-1,800.00mm, Gr.8.8, full length treated stud, 2,112.00 nos)

   3.d. Provide and install steel plate (3,000.00mmx220.00mmx22.00mm, S355 quality, 352.00 nos)

   3.e. Filling high-strength, cement based grout over and under the plates

28
29
36
38
41
42

Steel Bracing of B-Axis Beams on Top of the Dock