Employer         : İSDEMİR-İskenderun Iron and Steel Co. – İskenderun, Hatay, Türkiye

Project Name     : Renewal of İSDEMİR A1 (No. 1) Dock Ore Unloading Cranes rails, Including All Underlying Works, Renewal of Railway Rails, Including All underlying Works and Renewal Of Dock concrete Pavement

Start Date           : 2022

Finish Date        : 2023

Scope of Work  : 

 

Concrete breaking, excavation and filling works, placement of anchor rods with epoxy-based chemicals, grouting, manufacturing and installation of under-rail plates, rail clips and rail pads, asphalt concrete binder layer and renewal of  concrete dock pavement

 

  1. Manufacturing and Placement of Embedded Steel Elements (284.71 tons)

  2. Concrete Drilling and Installation of Anchor Rods by Epoxy Material (3,141.08 m)

  3. Supply and Pouring Cement Based Grout and  C40 Self-levelling Concrete (200.50 cu.m)  (164.82 cu.m)

  4. Demolish Reinforced Concrete (1,822.66 cu.m), Formwork (1.040,00 sq.m), Steel Mesh Reinforcement Supply and Installation (63,46 tons)  and Concrete Pavement using C30/37 Concrete (8,183.76 sq.m)

  5. Structural Steel Dismantling (558.11 tons)

  6. Installation of CR 73 Crane Rail (2,860.00 m)

  7. Installation of Rail Clips (11,400.00 nos)

  8. Rail Pad Installation (1,900.00 m)

  9. Aluminatermit Welding (138.00 nos)

  10. Manufacturing and Installation of Storm Lock  (8.00 nos) and Installation of Storm Lock (60.00 nos)

 

Resim1
Resim2

Welding Rails with Aluminatermit Welding Method

Plate, Clip, Pad and Rail Mountings Completed, Crane Rails Ready for Under-Rail Grout Application

Resim3
Resim4

Application of Asphaltic Concrete Binder Between Rails and Completed Crane Rails